Progress Report -

Submitted by -: Vaibhav Thakur (8916816)

Sherry Sharma ()

Sukhpreet Singh ()

Managing Improvement projects

QUAL

Process Quality Engineering

Submitted to -: Professor Veronica

Date- 04 November 2023

Executive Summary

This report seeks to conduct a project on calculating the Overall Equipment Effectiveness during a Product

Line Testing that began on October 11, 2023, and will conclude on December 12, 2023, including

downtime, slow cycles, and rejects. The project has been underway for more than two months, and while it

is progressing well and receiving solid support from all stakeholders involved, we still anticipate finishing

it within the allotted time frame. This represents the team's current work progress. Kindly refer to the

information in the following parts, which include:

1. Project Charter

2. Work Breakdown Structure (WBS)

3. Cost Estimate

4. Gantt Chart (Project Milestone)

2. Work Breakdown Structure (WBS)

The project is divided into 8 main groups and each further divided into small sub groups until it can not be broken -

Improvement Project

Project
Initiating &
Planning
Real Time
Monitoring
Performance
Tracking
Reporting
Validation
Data Testing
Analysis
Report
Generation
Report
Review &
Validation
Financial
Closure
Final Stakeholder
Communication
Documentation
& Reporting
Implementation
Review
Change
Management
Strategies
Resource
Allocation
Scope
Variation
Full
Implementation
Training
& Testing
Software
Integration
System
Configuration
Software
Selection
Data
Review &
Validation
Check
Data
Collection
Procedure
Data Source
Identification
Current
Quality
Status
Current
Performance
Status
Set
Objectives
& Targets
Current
Equipment
status
Define
Measurement
Process
Testing &
Validation
Data
Collection
OEE Software
Implementation
Data Analysis
& Reporting
Full
Implementation
Continuous
Monitoring
Project
Review &
Closure
Review

3. Cost Estimation

The list of activities serves as the basis for the cost estimate; as previously mentioned, each activity is related to the WBS. After that, we estimated the
duration of each activity, allocated the resources, and computed the estimated expenses. Further information is provided below. Thus, $29,416 is the
estimated total cost.

HUMAN RESOURCES COST ESTIMATES

Activity
Duration
(days) Resource %Allocated
Daily
Rate Cost
Initiating Phase

Define Measurement Process 1 Project Manager 50% $ 800 $ 400

Total Initiating Phase $ 400
Planning Phase

Current Equipment status 1 Planning Team 100% $ 560 $ 560

Set Objectives & Targets 1 Assistant Manager 1 70% $ 720 $ 504

Current Performance Status 1 Planning Team 100% $ 560 $ 560

Current Quality Status 1 Planning Team 100% $ 560 $ 560

Total Planning Phase $ 2,

Executing Phase

Data Collection

Data Source Identification 1 Data Collection Team 100% $ 560 $ 560

Data Collection Procedure 3 Data Collection Team 100% $ 560 $ 1,

Data Review & Validation 1 Data Collection Team 100% $ 560 $ 560

OEE Software Implementation

Software Selection 1 Implementation Team 100% $ 560 $ 560

System Configuration 2 Implementation Team 100% $ 560 $ 1,

Software Integration 3 Implementation Team 100% $ 560 $ 1,

Training & Testing 1 Implementation Team 100% $ 560 $ 560

Full Implementation 2 Implementation Team 100% $ 560 $ 1,

Data Analysis & Reporting

Data Analysis 2 Assistant Manager 1 50% $ 720 $ 720

Report Generation 2 Assistant Manager 2 50% $ 640 $ 640

Report Review & Validation 2 Project Manager 50% $ 800 $ 800

Testing & Validation

Testing 1 Testing & Validation Team 100% $ 480 $ 480

Resources Hourly rate Daily Rate
Project Manager $100/hr $ 800
Assistant Manager 1 $90/hr $ 720
Assistant Manager 2 $80/hr $ 640
Planning Team $70/hr $ 560
Data Collection Team $70/hr $ 560
Implementation Team $70/hr $ 560
Testing & Validation Team $60/hr $ 480

4. Gant Chart

The Gantt chart is attached.
Was this document helpful?

Group 9 Report

Course: QUALITY, STRATEGY AND VALUE CREATION (QUAL8000)

133 Documents
Students shared 133 documents in this course

University: Conestoga College

Was this document helpful?
Progress Report -1
Submitted by -: Vaibhav Thakur (8916816)
Sherry Sharma ()
Sukhpreet Singh ()
Managing Improvement projects
QUAL8190
Process Quality Engineering
Submitted to -: Professor Veronica
Date- 04 November 2023