Skip to document

Construction planning scheduling

Nil
Course

Civil Engineering (CE)

999+ Documents
Students shared 1445 documents in this course
University

Anna University

Academic year: 2022/2023
Uploaded by:
0followers
1Uploads
0upvotes

Comments

Please sign in or register to post comments.

Preview text

UNIT-

Construction Planning

1 Basic Concepts in the Development of Construction Plans

Construction planning is a fundamental and challenging activity in the management and

execution of construction projects. It involves the

 Choice of technology

 Definition of work tasks

 The estimation of the required resources and durations for individual

tasks,

 The identification of any interactions among the different work tasks.

A good construction plan is the basis for developing the budget and the schedule for work.

Developing the construction plan is a critical task in the management of construction, even if

the plan is not written or otherwise formally recorded. In addition to these technical aspects

of construction planning, it may also be necessary to make organizational decisions about the

relationships between project participants and even which organizations to include in a

project.

Sherlock Holmes noted that forming a construction plan is a highly challenging task.

Essential aspects of construction planning include the

 Generation of required activities.

 Analysis of the implications of these activities.

 Choice among the various alternative means of performing activities.

In developing a construction plan, it is common to adopt a primary emphasis on either cost

control or on schedule control as illustrated in Fig. Some projects are primarily divided into

expense categories with associated costs. In these cases, construction planning is cost or

expense oriented.

Alternative Emphases in Construction Planning

DIRECT COST:

Amount spend for things which are directly involved in the project

 Equipment.

 Materials.

 Labour cost etc.

INDIRECT COST:

Indirectly help to develop the project.

 Borrowing expenses for project financing

 Supervisor’s salary etc.

For some projects, scheduling of work activities over time is critical and is emphasized in the

planning process. In this case, the planner insures that the proper precedence among

activities is maintained and that efficient scheduling of the available resources prevails.

Traditional scheduling procedures emphasize the maintenance of task precedence (resulting

in critical path scheduling procedures) or efficient use of resources over time (resulting

in job shop scheduling procedures).

computer aided design (CAD) system may be helpful in simulating space requirements for

operations and for identifying any interference. Similarly, problems in resource availability

identified during the simulation of the construction process might be effectively forestalled

by providing additional resources as part of the construction plan.

Example: Roadway rehabilitation

An example from a roadway rehabilitation project in Pittsburgh, PA can serve to

illustrate the importance of good construction planning and the effect of technology choice.

In this project, the decks on overpass bridges as well as the pavement on the highway itself

were to be replaced. The initial construction plan was to work outward from each end of the

overpass bridges while the highway surface was replaced below the bridges. As a result,

access of equipment and concrete trucks to the overpass bridges was a considerable problem.

However, the highway work could be staged so that each Overpass Bridge was accessible

from below at prescribed times. By pumping concrete up to the overpass bridge deck from

the highway below, costs were reduced and the work was accomplished much more quickly.

1 Defining Work Tasks

The terms work "tasks" or "activities" are often used interchangeably in construction

plans to refer to specific, defined items of work. In job shop or manufacturing terminology, a

project would be called a "job" and an activity called an "operation", but the sense of the

terms is equivalent. The scheduling problem is to determine an appropriate set of activity

start time, resource allocations and completion times that will result in completion of the

project in a timely and efficient fashion. In this planning, defining work tasks, technology

and construction method is typically done either simultaneously or in a series of iterations.

The definition of appropriate work tasks can be a laborious and tedious process, yet it

represents the necessary information for application of formal scheduling procedures. Since

construction projects can involve thousands of individual work tasks, this definition phase

can also be expensive and time consuming. Fortunately, many tasks may be repeated in

Road below the
bridge
Surface replacement
work
Over passage bridge

different parts of the facility or past facility construction plans can be used as general models

for new projects. For example, the tasks involved in the construction of a building floor may

be repeated with only minor differences for each of the floors in the building. While

repetition of activities in different locations or reproduction of activities from past projects

reduces the work involved, there are very few computer aids for the process of defining

activities. More formally, an activity is any subdivision of project tasks. The set of activities

defined for a project should be comprehensive or completely exhaustive so that all necessary

work tasks are included in one or more activities.

The time required to perform an activity is called the duration of the activity. The

beginning and the end of activities are signposts or milestones, indicating the progress of the

project. Occasionally, it is useful to define activities which have no duration to mark

important events. For example, receipt of equipment on the construction site may be defined

as an activity since other activities would depend upon the equipment availability and the

project manager might appreciate formal notice of the arrival. Similarly, receipt of regulatory

approvals would also be specially marked in the project plan.

The extent of work involved in any one activity can vary tremendously in construction

project plans. A result of this process is a natural hierarchy of activities with large, abstract

functional activities repeatedly sub-divided into more and more specific sub-tasks. For

example, the problem of placing concrete on site would have sub-activities associated with

placing forms, installing reinforcing steel, pouring concrete, finishing the concrete, removing

forms and others. Even more specifically, sub-tasks such as removal and cleaning of forms

after concrete placement can be defined. Even further, the sub-task "clean concrete forms"

could be subdivided into the various operations:

 Transport forms from on-site storage and unload onto the cleaning station.

 Position forms on the cleaning station.

 Wash forms with water.

 Clean concrete debris from the form's surface.

 Coat the form surface with an oil release agent for the next use.

 Unload the form from the cleaning station and transport to the storage location.

This detailed task breakdown of the activity "clean concrete forms" would not generally

be done in standard construction planning, but it is essential in the process of programming

or designing a robot to undertake this activity since the various specific tasks must be well

defined for a robot implementation.

It is generally advantageous to introduce an explicit hierarchy of work activities for the

purpose of simplifying the presentation and development of a schedule. For example, the

initial plan might define a single activity associated with "site clearance."

Figure Illustrative Hierarchical Activity Divisions for a Roadway Project

1 Defining Precedence Relationships Among Activities

Once work activities have been defined, the relationships among the activities can be

specified. Precedence relations between activities signify that the activities must take place

in a particular sequence. Diagrammatically, precedence relationships can be illustrated by a

network or graph in which the activities are represented by arrows as in Figure.

Road Building Project with two culverts

Structures Roadway General
Culverts
Earthwork
Pavement
Excavation
Filling
Finishing
Watering Compaction Paving
Structural
excavation
Concreting Reinforcement
Excavation
Manual
Concrete
Batching
Concrete
Filling

The arrows in Figure are called branches or links in the activity network, while the circles

marking the beginning or end of each arrow are called nodes or events. In this figure, links

represent particular activities, while the nodes represent milestone events.

Figure Illustrative Set of Four Activities with Precedence

More complicated precedence relationships can also be specified. For example, one activity

might not be able to start for several days after the completion of another activity. As a

common example, concrete might have to cure (or set) for several days before formwork is

removed. This restriction on the removal of forms activity is called a lag between the

completion of one activity (i., pouring concrete in this case) and the start of another activity

(i., removing formwork in this case).

Three mistakes should be avoided in specifying predecessor relationships for construction

plans.

 First, a circle of activity precedences will result in an impossible plan. For example,

if activity A precedes activity B, activity B precedes activity C, and activity C

precedes activity A, then the project can never be started or completed.

Figure - Example of an Impossible Work Plan

 Forgetting a necessary precedence relationship can be more insidious. For

example, suppose that installation of dry wall should be done prior to floor finishing.

Ignoring this precedence relationship may result in both activities being scheduled at

the same time. Corrections on the spot may result in increased costs or problems of

quality in the completed project.

 Activities cannot be superseded.

prepared, so that activity E (trench excavation) is a preceding activity. We also assume that

the utilities should not be installed until grading is completed to avoid equipment conflicts,

so activity D (general grading) is also preceding activities G (install sewers) and H (install

utilities). Finally, activity I (pour concrete) cannot begin until the sewer line is installed and

formwork and reinforcement are ready, so activities F and G are preceding. Other utilities

may be routed over the slab foundation, so activity H (install utilities) is not necessarily

a preceding activity for activity I (pour concrete). The result of our planning is the immediate

precedence shown in Table.

TABLE Precedence Relations for a Nine-Activity Project Example
Activity Description Predecessors
A B C D E F G H I
Site clearing
Removal of trees
General excavation
Grading general area
Excavation for utility trenches
Placing formwork and reinforcement for concrete
Installing sewer lines
Installing other utilities
Pouring concrete
---
---
A
A
B,C
B,C
D,E
D,E
F,G

Figure Activity-on-Branch Representation of a Nine Activity Project

Alternatively, the nine activities could be represented by nodes and predecessor relationships

by branches or links, as in Figure. The result is an activity-on-node diagram. In Figure 9-6,

new activity nodes representing the beginning and the end of construction have been added

to mark these important milestones.

These network representations of activities can be very helpful in visualizing the various

activities and their relationships for a project. Whether activities are represented as branches

(as in Figure) or as nodes (as in Figure) is largely a matter of organizational or personal

choice. Some considerations in choosing one form or another are discussed in Chapter 10.

Figure Activity-on-Node Representation of a Nine Activity Project

It is also notable that Table lists only the immediate predecessor relationships. Clearly, there

are other precedence relationships which involve more than one activity. For example,

"installing sewer lines" (activity G) cannot be undertaken before "site clearing" (Activity A)

is complete since the activity "grading general area" (Activity D) must precede activity G

and must follow activity A. Table is an implicit precedence list since only immediate

predecessors are recorded. An explicit predecessor list would include all of the preceding

activities for activity G. Table 9-2 shows all such predecessor relationships implied by the

project plan. This table can be produced by tracing all paths through the network back from a

particular activity and can be performed algorithmically.

TABLE All Activity Precedence Relationships for a Nine-Activity Project
Predecessor Activity Direct Successor Activities All Successor Activities All Predecessor Activities
A B C D E F G H I
C,D
E,F
E,F
G,H
G,H
I
I
---
---
E,F,G,H,I
G,H,I
G,H,I
I
I
---
---
---
---
---
---
A
A
A,B,C
A,B,C
A,B,C,D,E
A,B,C,D,E
A,B,C,D,E,F,G

1 Estimating Activity Durations

In most scheduling procedures, each work activity has associated time duration. These

durations are used extensively in preparing a schedule. For example, suppose that the

durations shown in Table were estimated for the project diagrammed in Figure.

contractors and the owner. The number of crews working, Nij, is decided by the planner. In

many cases, the number or amount of resources applied to particular activities may be

modified in light of the resulting project plan and schedule. Finally, some estimate of the

expected work productivity, Pij must be provided to apply Equation (1). As with cost

factors, commercial services can provide average productivity figures for many standard

activities of this sort. Historical records in a firm can also provide data for estimation of

productivities.

The calculation of a duration as in Equation (1) is only an approximation to the actual

activity duration for a number of reasons. First, it is usually the case that peculiarities of the

project make the accomplishment of a particular activity more or less difficult. For example,

access to the forms in a particular location may be difficult; as a result, the productivity of

assembling forms may be lower than the average value for a particular project. Often,

adjustments based on engineering judgment are made to the calculated durations from

Equation (1) for this reason.

In addition, productivity rates may vary in both systematic and random fashions from the

average. An example of systematic variation is the effect of learning on productivity. As a

crew becomes familiar with an activity and the work habits of the crew, their productivity

will typically improve. Figure illustrates the type of productivity increase that might occur

with experience; this curve is called a learning curve. The result is that productivity Pij is a

function of the duration of an activity or project. A common construction example is that the

assembly of floors in a building might go faster at higher levels due to improved productivity

even though the transportation time up to the active construction area is longer. Again,

historical records or subjective adjustments might be made to represent learning curve

variations in average productivity.

Figure Illustration of Productivity Changes Due to Learning

Random factors will also influence productivity rates and make estimation of activity

durations uncertain. For example, a scheduler will typically not know at the time of making

the initial schedule how skillful the crew and manager will be that are assigned to a

particular project. The productivity of a skilled designer may be many times that of an

unskilled engineer. In the absence of specific knowledge, the estimator can only use average

values of productivity.

Weather effects are often very important and thus deserve particular attention in estimating

durations. Weather has both systematic and random influences on activity durations.

Whether or not a rainstorm will come on a particular day is certainly a random effect that

will influence the productivity of many activities. However, the likelihood of a rainstorm is

likely to vary systematically from one month or one site to the next. Adjustment factors for

inclement weather as well as meteorological records can be used to incorporate the effects of

weather on durations. As a simple example, an activity might require ten days in perfect

weather, but the activity could not proceed in the rain. Furthermore, suppose that rain is

expected ten percent of the days in a particular month. In this case, the expected activity

duration is eleven days including one expected rain day.

Finally, the use of average productivity factors themselves cause problems in the calculation

presented in Equation (1). The expected value of the multiplicative reciprocal of a variable

is not exactly equal to the reciprocal of the variable's expected value. For example, if

productivity on an activity is either six in good weather (ie., P=6) or two in bad weather (ie.,

P=2) and good or bad weather is equally likely, then the expected productivity is P = (6)(0)

+ (2)(0) = 4, and the reciprocal of expected productivity is 1/4. However, the expected

reciprocal of productivity is E[1/P] = (0)/6 + (0)/2 = 1/3. The reciprocal of expected

productivity is 25% less than the expected value of the reciprocal in this case! By

representing only two possible productivity values, this example represents an extreme case,

but it is always true that the use of average productivity factors in Equation (1) will result

in optimistic estimates of activity durations. The use of actual averages for the reciprocals of

productivity or small adjustment factors may be used to correct for this non-linearity

problem.

The simple duration calculation shown in Equation (1) also assumes an inverse linear

relationship between the number of crews assigned to an activity and the total duration of

work. While this is a reasonable assumption in situations for which crews can work

independently and require no special coordination, it need not always be true. For example,

design tasks may be divided among numerous architects and engineers, but delays to insure

proper coordination and communication increase as the number of workers increase. As

another example, insuring a smooth flow of material to all crews on a site may be

increasingly difficult as the number of crews increase. In these latter cases, the relationship

between activity duration and the number of crews is unlikely to be inversely proportional as

shown in Equation (1). As a result, adjustments to the estimated productivity from

Equation (1) must be made. Alternatively, more complicated functional relationships might

the variability of duration times; the variance is the value of the standard deviation

multiplied by itself. From historical data, these two parameters can be estimated as:

(1)
(1)

Where we assume that n different observations xk of the random variable x are available.

This estimation process might be applied to activity durations directly (so that xk would be a

record of an activity duration Dij on a past project) or to the estimation of the distribution of

productivities (so that xk would be a record of the productivity in an activity Pi) on a past

project) which, in turn, is used to estimate durations using Equation (1). If more accuracy

is desired, the estimation equations for mean and standard deviation, Equations (1) and

(1) would be used to estimate the mean and standard deviation of the reciprocal of

productivity to avoid non-linear effects. Using estimates of productivities, the standard

deviation of activity duration would be calculated as:

(1)

where is the estimated standard deviation of the reciprocal of productivity that is

calculated from Equation (1) by substituting 1/P for x.

1 Estimating Resource Requirements for Work Activities

In addition to precedence relationships and time durations, resource

requirements are usually estimated for each activity. Since the work activities defined for a

project are comprehensive, the total resources required for the project are the sum of the

resources required for the various activities. By making resource requirement estimates for

each activity, the requirements for particular resources during the course of the project can

be identified. Potential bottlenecks can thus be identified, and schedule, resource allocation

or technology changes made to avoid problems.

Many formal scheduling procedures can incorporate constraints imposed by the availability

of particular resources. For example, the unavailability of a specific piece of equipment or

crew may prohibit activities from being undertaken at a particular time. Another type of

resource is space. A planner typically will schedule only one activity in the same location at

the same time. While activities requiring the same space may have no necessary technical

precedence, simultaneous work might not be possible.

The initial problem in estimating resource requirements is to decide the extent and number of

resources that might be defined. At a very aggregate level, resources categories might be

limited to the amount of labor (measured in man-hours or in dollars), the amount of materials

required for an activity, and the total cost of the activity. At this aggregate level, the resource

estimates may be useful for purposes of project monitoring and cash flow planning. For

example, actual expenditures on an activity can be compared with the estimated required

resources to reveal any problems that are being encountered during the course of a project.

More detailed definitions of required resources would include the number and type of both

workers and equipment required by an activity as well as the amount and types of materials.

Standard resource requirements for particular activities can be recorded and adjusted for the

special conditions of particular projects. As a result, the resources types required for

particular activities may already be defined. Reliance on historical or standard activity

definitions of this type requires a standard coding system for activities.

In making adjustments for the resources required by a particular activity, most of the

problems encountered in forming duration estimations described in the previous section are

also present. In particular, resources such as labor requirements will vary in proportion to the

work productivity, Pij, used to estimate activity durations in Equation (1). Mathematically,

a typical estimating equation would be:

where Rkij are the resources of type k required by activity ij, Dij is the duration of activity ij,

Nij is the number of standard crews allocated to activity ij, and Ukij is the amount of resource

type k used per standard crew. For example, if an activity required eight hours with two

crews assigned and each crew required three workers, the effort would be R = 823 = 48

labor-hours.

From the planning perspective, the important decisions in estimating resource requirements

are to determine the type of technology and equipment to employ and the number of crews to

allocate to each task. Clearly, assigning additional crews might result in faster completion of

a particular activity. However, additional crews might result in congestion and coordination

problems, so that work productivity might decline.

Example: Pouring Concrete Slabs

For large concrete pours on horizontal slabs, it is important to plan the activity so that the

slab for a full block can be completed continuously in a single day. Resources required for

TABLE 1.7 Major Divisions in the Uniform Construction Index
0 Conditions of the contract
1 General requirements
2 Site work
3 Concrete
4 Masonry
5 Metals
6 Wood and plastics
7 Thermal and moisture prevention
8 Doors and windows
9 Finishes
10 Specialties
11 Equipment
12 Furnishings
13 Special construction
14 Conveying system
15 Mechanical
16 Electrical

While MASTERFORMAT provides a very useful means of organizing and communicating

information, it has some obvious limitations as a complete project coding system. First, more

specific information such as location of work or responsible organization might be required

for project cost control. Code extensions are then added in addition to the digits in the basic

MASTERFORMAT codes. For example, a typical extended code might have the following

elements:

0534.02220. A.00

The first four digits indicate the project for this activity; this code refers to an activity on

project number 0534. The next five digits refer to the MASTERFORMAT secondary

division; referring to Table 1.7, this activity would be 02220 "Excavating, Backfilling and

Compacting." The next two digits refer to specific activities defined within this

MASTERFORMAT code; the digits 21 in this example might refer to excavation of column

footings. The next character refers to the block or general area on the site that the activity

will take place; in this case, block A is indicated. The digits 00 could be replaced by a code

to indicate the responsible organization for the activity. Finally, the characters cf34 refer to

the particular design element number for which this excavation is intended; in this case,

column footing number 34 is intended. Thus, this activity is to perform the excavation for

column footing number 34 in block A on the site. Note that a number of additional activities

would be associated with column footing 34, including formwork and concreting. Additional

fields in the coding systems might also be added to indicate the responsible crew for this

activity or to identify the specific location of the activity on the site (defined, for example, as

x, y and z coordinates with respect to a base point).

As a second problem, the MASTERFORMAT system was originally designed for building

construction activities, so it is difficult to include various construction activities for other

types of facilities or activities associated with planning or design. Different coding systems

have been provided by other organizations in particular sub-fields such as power plants or

roadways. Nevertheless, MASTERFORMAT provides a useful starting point for organizing

information in different construction domains.

TABLE 1.7 Secondary Divisions in MASTERFORMAT for Site Work
02-
02-
02-
Subsurface investigation
Standard penetration tests
Seismic investigation
02-
02-
02-
02-
02-
Demolition
Building demolition
Selective demolition
Concrete removal
Asbestos removal
02-
02-
02-
02-
Site preparation
Site clearing
Selective clearing
Structure moving
02-140 Dewatering
02-150 Shoring and underpinning
02-160 Excavation supporting system
02-170 Cofferdams
02-
02-
02-
02-
02-
02-
02-
02-
02-
Earthwork
Grading
Excavating, backfilling and compaction
Base course
Soil stabilization
Vibro-floatation
Slope protection
Soil treatment
Earth dams
02-
02-
02-
02-
02-
02-
Tunneling
Tunnel ventilation
Tunnel excavating
Tunnel lining
Tunnel grouting
Tunnel support systems
02-
02-
02-
02-
02-
Piles and caissons
Pile driving
Driven piles
Bored/augered piles
Caissons
02-450 Railroad work
02-480 Marine work
02-
02-
02-
02-
02-
02-
02-
02-
02-
02-
02-
Paving and surfacing
Walk, road and parking paving
Unit pavers
Curbs
Athletic paving and surfacing
Synthetic surfacing
Surfacing
Highway paving
Airfield paving
Pavement repair
Pavement marking
02-600 Piped utility materials
02-660 Water distribution
02-680 Fuel distribution
02-700 Sewage and drainage
02-760 Restoration of underground pipelines
02-770 Ponds and reservoirs
02-800 Power and communications
02-880 Site improvements
02-900 Landscaping
Was this document helpful?

Construction planning scheduling

Course: Civil Engineering (CE)

999+ Documents
Students shared 1445 documents in this course

University: Anna University

Was this document helpful?
2
UNIT-1
Construction Planning
1.1 Basic Concepts in the Development of Construction Plans
Construction planning is a fundamental and challenging activity in the management and
execution of construction projects. It involves the
Choice of technology
Definition of work tasks
The estimation of the required resources and durations for individual
tasks,
The identification of any interactions among the different work tasks.
A good construction plan is the basis for developing the budget and the schedule for work.
Developing the construction plan is a critical task in the management of construction, even if
the plan is not written or otherwise formally recorded. In addition to these technical aspects
of construction planning, it may also be necessary to make organizational decisions about the
relationships between project participants and even which organizations to include in a
project.
Sherlock Holmes noted that forming a construction plan is a highly challenging task.
Essential aspects of construction planning include the
Generation of required activities.
Analysis of the implications of these activities.
Choice among the various alternative means of performing activities.
In developing a construction plan, it is common to adopt a primary emphasis on either cost
control or on schedule control as illustrated in Fig. Some projects are primarily divided into
expense categories with associated costs. In these cases, construction planning is cost or
expense oriented.