- Information
- AI Chat
Was this document helpful?
Tilos for P16 P17-1 - A sample Time-Location -sequence for construction.
Course: Civil Engineering (BSCE 01)
136 Documents
Students shared 136 documents in this course
University: Ateneo de Davao University
Was this document helpful?
Schedule of Activities for Additional Foundation at P16 and P17 27 August 2023
General Activities
P16
Upstream
Downstream
P17
Upstream
Downstream
Crane Schedule
150 ton
60 ton Crawler Crane
60 ton Mobile Crane
Activities
Procurement of Materials
Water Jet Installation
400 Ton AK Crane
(Permanent)
350 Ton AK Crane
(Temporary)
Hirose
Shoei
Sub-Contractors
Suimei
20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F
January February March April
Underwater Exc. (8D)
Procurement of materials Sep 2023 -
January 2024
Water Jet Installation
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
May June
Stud
Prep
Stud Welding
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D) Conc. Inside SPSP
(6D)
Bot. Slab Conc.
(6D) Dry-Up Cofferdam and Ring Beam Installation (24D) Levelling Conc.
(7D)
Dry-Up Cofferdam and Ring Beam Installation (24D)
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D) Conc. Inside SPSP
(6D) Underwater Exc. (8D) Bot. Slab Conc.
(6D)
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D)
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
Levelling Con
(7D)
Stud
Prep
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D)
Conc. Inside SPSP
(6D)
Conc. Inside SPSP
(6D) Underwater Exc. (8D)
Bot. Slab Conc.
(6D)
150 Ton CC
150 Ton CC
150 Ton CC
150 Ton CC
150 Ton CC
150 Ton CC
150
400 Ton CC (AK)
400 Ton CC (AK)
400 Ton CC (AK)
400 Ton CC (AK)
350 Ton CC (AK)
350 Ton CC (AK)
350 Ton CC (AK)
350 Ton CC (AK)
150 Ton CC
150 Ton CC
400 Ton CC (AK)
60 Ton MC
60 Ton MC
60 Ton MC
60 Ton MC
60 Ton CC
350 Ton CC(AK)
Students also viewed
Related documents
- Chapter II - RRL - rrl for thesis initial draft (not final)
- BOLO PAA5 - Five Examples of Primary Sources
- Rationale
- 480611738 Gen Math11 Q1 Mod10 solving real life problems involving rational 08082020 pdf
- The geologic and topographic structures of the ocean floor primarily reflect plate tectonic activity that has occurred over the past 150 million years of the 4
- Physics Laws of Motion Part 1 Reviewer