Schedule of Activities for Additional Foundation at P16 and P17 27 August 2023

General Activities

P

Upstream

Downstream

P

Upstream

Downstream

Crane Schedule

150 ton

60 ton Crawler Crane

60 ton Mobile Crane

Activities

Procurement of Materials

Water Jet Installation

400 Ton AK Crane

(Permanent)

350 Ton AK Crane

(Temporary)

Hirose

Shoei

Sub-Contractors

Suimei

20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F

January February March April

Underwater Exc. (8D)

Procurement of materials Sep 2023 -January 2024

Water Jet Installation

Guide Frame Installation

(10D)

Drive Piling Permanent Piles

(7 nos.) (14D)

May June

Stud

Drive Piling Temporary Piles (4 nos.) (24D) Prep Stud Welding

Guide Frame Removal

(8D) Joint Grouting (9D) Water Proofing (14D)

Conc. Inside SPSP(6D) Bot. Slab Conc.

(6D) Dry-Up Cofferdam and Ring Beam Installation (24D)

Levelling Conc.

(7D)

Dry-Up Cofferdam and Ring Beam Installation (24D)

Guide Frame Installation

(10D)

Drive Piling Permanent Piles

(7 nos.) (14D)

Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal(8D) Joint Grouting (9D) Water Proofing (14D) Conc. Inside SPSP(6D) Underwater Exc. (8D) Bot. Slab Conc.(6D)

Guide Frame Installation

(10D)

Drive Piling Permanent Piles

(7 nos.) (14D)

Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal(8D) Joint Grouting (9D) Water Proofing (14D)

Guide Frame Installation

(10D)

Drive Piling Permanent Piles

(7 nos.) (14D)

Levelling Con

(7D)

Stud

Prep

Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal(8D) Joint Grouting (9D) Water Proofing (14D) Conc. Inside SPSP (6D)

Conc. Inside SPSP

(6D) Underwater Exc. (8D)

Bot. Slab Conc.

(6D)

150 Ton CC

150 Ton CC

150 Ton CC

150 Ton CC

150 Ton CC

150 Ton CC

150

400 Ton CC (AK)

400 Ton CC (AK)

400 Ton CC (AK)

400 Ton CC (AK)

350 Ton CC (AK)

350 Ton CC (AK)

350 Ton CC (AK)

350 Ton CC (AK)

150 Ton CC

150 Ton CC

60 Ton MC 400 Ton CC (AK)

60 Ton MC

60 Ton MC

60 Ton MC

60 Ton CC

350 Ton CC(AK)

Schedule of Activities for Additional Foundation at P16 and P17 27 August 2023

General Activities

P

Upstream

Downstream

P

Upstream

Downstream

Crane Schedule

150 ton

60 ton Crawler Crane

60 ton Mobile Crane

Activities

Procurement of Materials

Water Jet Installation

400 Ton AK Crane

(Permanent)

350 Ton AK Crane

(Temporary)

Hirose

Shoei

Sub-Contractors

Suimei

29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S

July August September October November

Stud Welding Top Slab Construction (12D) Cutting of SPSP(6D)

Cutting of SPSP

(6D)

Levelling Conc.

(7D) Stud Welding

Top Slab Construction (12D)

Cutting of SPSP

(6D)

Stud

Prep

Underwater Exc. (8D) Bot. Slab Conc.(6D) Dry-Up Cofferdam and Ring Beam Installation (24D) Levelling Conc.(7D) Stud Welding Top Slab Construction (12D)

Top Slab Construction (12D) Cutting of SPSP(6D)

Stud

Prep

elling Conc.

Stud

Prep

Stud Welding

e SPSP

onc. Dry-Up Cofferdam and Ring Beam Installation (24D)

150 Ton CC

150 Ton CC

150 Ton CC

150 Ton CC

150 Ton CC

60 Ton MC

60 Ton MC

60 Ton CC

350 Ton C (AK)

Was this document helpful?

Tilos for P16 P17-1 - A sample Time-Location -sequence for construction.

Course: Civil Engineering (BSCE 01)

136 Documents
Students shared 136 documents in this course
Was this document helpful?
Schedule of Activities for Additional Foundation at P16 and P17 27 August 2023
General Activities
P16
Upstream
Downstream
P17
Upstream
Downstream
Crane Schedule
150 ton
60 ton Crawler Crane
60 ton Mobile Crane
Activities
Procurement of Materials
Water Jet Installation
400 Ton AK Crane
(Permanent)
350 Ton AK Crane
(Temporary)
Hirose
Shoei
Sub-Contractors
Suimei
20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F S Su M T W Th F
January February March April
Underwater Exc. (8D)
Procurement of materials Sep 2023 -
January 2024
Water Jet Installation
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
May June
Stud
Prep
Stud Welding
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D) Conc. Inside SPSP
(6D)
Bot. Slab Conc.
(6D) Dry-Up Cofferdam and Ring Beam Installation (24D) Levelling Conc.
(7D)
Dry-Up Cofferdam and Ring Beam Installation (24D)
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D) Conc. Inside SPSP
(6D) Underwater Exc. (8D) Bot. Slab Conc.
(6D)
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D)
Guide Frame Inst allation
(10D)
Drive Piling Permanent Piles
(7 nos.) (14D)
Levelling Con
(7D)
Stud
Prep
Drive Piling Temporary Piles (4 nos.) (24D) Guide Frame Removal
(8D) Joint Grout ing (9D) Water Proofing (14D)
Conc. Inside SPSP
(6D)
Conc. Inside SPSP
(6D) Underwater Exc. (8D)
Bot. Slab Conc.
(6D)
150 Ton CC
150 Ton CC
150 Ton CC
150 Ton CC
150 Ton CC
150 Ton CC
150
400 Ton CC (AK)
400 Ton CC (AK)
400 Ton CC (AK)
400 Ton CC (AK)
350 Ton CC (AK)
350 Ton CC (AK)
350 Ton CC (AK)
350 Ton CC (AK)
150 Ton CC
150 Ton CC
400 Ton CC (AK)
60 Ton MC
60 Ton MC
60 Ton MC
60 Ton MC
60 Ton CC
350 Ton CC(AK)